| Power Sector at a Glance
"ALL INDIA"
As on 31-03-2012
Source:CEA |
|
|
|
|
|
|
| 1.Total Installed Capacity: |
Power for All by 2012 |
|
| Sector |
MW |
%age |
| State Sector |
85,918.65 |
42.98 |
| Central Sector |
59,682.63 |
29.85 |
| Private Sector |
54,275.75 |
27.15 |
| Total |
1,99,877.03
|
|
|

|
|
| Fuel |
MW |
%age |
| Total Thermal |
131603.18
|
65.84
|
Coal |
112,022.38 |
56.04 |
Gas |
18,381.05 |
9.19 |
Oil |
1,199.75 |
0.60 |
| Hydro
(Renewable) |
38,990.40 |
19.50 |
| Nuclear |
4,780.00 |
2.39 |
| RES** (MNRE) |
24,503.45 |
12.25 |
| Total |
1,99,877.03
|
100.00 |
Renewable Energy Sources(RES) include SHP, BG, BP, U&I and Wind Energy
SHP= Small Hydro Project ,BG= Biomass Gasifier ,BP= Biomass Power,
U & I=Urban & Industrial Waste Power, RES=Renewable Energy Sources
Note:-
The generation stations with installed capacity less than or equal to 25 MW are indicated under RES.
The installed capacity in respect of RES as on 31.03.2012 is based on
MNRE email of dated 10.04.12 from Ministry of Renewable Energy where cumulative
Grid interactive power installed capacity has been indicated as 24914.32
MW as on 31.03.2012.(Reconciliation of installed capacity of Hydro capacity
resulted in transfer of 135 MW from conventional to SHP-RES and retrieval
of installed capacity of 67.20 from SHP-RES to conventional Hydro has
resulted in net addition of 67.8 MW to SHP under RES. Also 30 MW of capacity
in the nature of Waste Heat Recovery Power Plant at Goa Energy Private
Limited under U&I category of RES. Out of this installed capacity due
to wind and small hydro amounting to 508.67 MW appearing in captive capacity
has been deducted to arrive at installed capacity of utilities in respect
of RES.(24914.32-508.67+67.8+30=24503.45)).
10% of the Installed capacity of Pragati CCGT which is indicated to be Merchant Power by IRP Div has been included in I/C of Delhi State Sector.
Ammendment warantted as intimation of inclusion of Mundra UMTPP(800MW) & Salaya TPP(600MW) in the Pvt. sector of Gujarat State recd after issue of Installed capacity statement.
The total Installed generating capacity retired during March 2012 was 155 MW (Barauni TPS Units Nos 1 & 2 of BSEB & Unit No 3 of Harduaganj T P S of UPRVUNL)
Figures at second place of decimal may not tally due to rounding off.
|