| ABT has been under discussion
since 1994 when M/s ECC, an ADB consultant, first supported it. GOI constituted
a National Task Force in February 1995. It had ten meetings till end 1998
where all the related issues were discussed. A draft notification was
prepared for issue by government. With effect from May 15,1999 the jurisdiction
was vested in the CERC. Papers were sent to the Commission in June 1999
by the MOP. The proceedings were held in the Commission from July 26 to
28, 1999. The ABT order dated January 4, 2000 of the Commission departs
significantly from the draft notification as also from the prevailing
tariff design.
Why ABT?
1. India plans to have an integrated National Grid.
This will assist in meeting demand with the least cost supply. Five Regional
grids already exist. Some linkages between Regions are also in place.
- The five Regional grids work at vastly varying operational parameters
today. Frequency level is one such operational parameter. The target
frequency prescribed by the Indian Electricity Rules is 50 Hz
- Integrated grid operations require the normalisation of frequency
across all five Regions. The alternative is to insulate each Regional
Grid by Back to Back HVDC links. This is an expensive option. Normalisation
of frequency requires proactive load management by beneficiaries and
despatch discipline by generators.
- There is currently no formal system of financial incentives to promote
grid discipline.
- The ABT provides this mechanism.
2. Chronic surpluses in the East and shortages in the
South, have resulted in sustained functioning of these grids at frequencies
which are far beyond even the normal band, liberally defined by the IEGC
as frequency variation within 49.5 to 50.3 Hz
- Continued functioning at non-standard frequency results in long-term
damages to both generation and end use equipment This is a “hidden
cost” which is borne by the customer in the long term.
- The ABT will induce corrections in the prevailing frequency to bring
it within the permissible band.
3. Frequent fluctuations in frequency caused by short-term
variations in the demand supply gap due to the tripping of load or outage
of a generator or a transmission line impose substantial costs on generators
and consumers.
- The ABT will address this problem by inducing grid discipline.
4. Economic efficiency dictates that least cost power
should be despatched in preference to more costly power (merit order despatch).
This becomes difficult without a two part tariff for all stations. States
tend to compare the total cost of central generators with the variable
cost of their own stations, since for them the fixed costs of state level
stations are sunk costs. This results in making central generation appear
artificially more expensive than state level stations even though on variable
cost basis the former may be cheaper.
- The two-part tariff of the ABT by making the payment of fixed cost
a fixed liability of the states converts it into a sunk cost thereby
leveling the playing field between central generators and state level
plants.
5. Currently beneficiaries are not liable for payment
of the fixed cost associated with the share of capacity allocated to them.
If a beneficiary decides not to draw any energy he can escape payment
of the fixed charge, which then gets paid by the person drawing energy.
This is unfair since it increases the cost of energy even for those beneficiaries
who may be drawing energy within their entitlements.
- The two-part tariff of the ABT assures that each beneficiary will
be liable for payment of the fixed cost associated with its share of
allocated generation capacity.
6. Currently generators have a perverse financial incentive
to go on generating even when there may be no demand. This results in
high frequency in the grid as is endemic in the East
- The ABT will discourage such behaviour by pricing generation outside
the schedule in relation to the prevailing frequency.
What Is ABT?
- It is a performance-based tariff for the supply of electricity by
generators owned and controlled by the central government
- It is also a new system of scheduling and despatch, which requires
both generators and beneficiaries to commit to day-ahead schedules.
- It is a system of rewards and penalties seeking to enforce day ahead
pre-committed schedules, though variations are permitted if notified
One and one half hours in advance.
- The order emphasises prompt payment of dues. Non-payment of prescribed
charges will be liable for appropriate action under sections 44 and
45 of the ERC Act.
It has three parts:
- A fixed charge (FC) payable every month by each beneficiary to the
generator for making capacity available for use. The FC is not the same
for each beneficiary. It varies with the share of a beneficiary in a generators
capacity. The FC, payable by each beneficiary, will also vary with the
level of availability achieved by a generator.
- In the case of thermal stations like those of NLC, where the fixed
charge has not already been defined separately by GOI notification,
it will comprise interest on loan, depreciation, O&M expenses, ROE,
Income Tax and Interest on working capital.
- In the case of hydro stations it will be the residual cost after
deducting the variable cost calculated as being 90% of the lowest variable
cost of thermal stations in a region.
- An energy charge (defined as per the prevailing operational cost norms)
per kwh of energy supplied as per a pre-committed schedule of supply drawn
upon a daily basis.
- A charge for Unscheduled Interchange (UI charge) for the supply and
consumption of energy in variation from the pre-committed daily schedule.
This charge varies inversely with the system frequency prevailing at the
time of supply/consumption. Hence it reflects the marginal value of energy
at the time of supply.
How is ABT different from normal proceedings to determine generation
tariff?
1. The ABT proceeding has not attempted to consider most of the cost
drivers like ROE, Operational Costs, depreciation rate, composition of
the Rate Base, capital structure etc. Proceedings to redefine these norms
are being held separately. Hence the ABT proceedings have been concerned
more with tariff design rather than definition of tariff norms or determination
of tariff levels.
2. It's incidence is a function not only of the behaviour of a generator
but also of the behaviour of a beneficiary. Disciplined beneficiaries
and generators stand to gain. Undisciplined beneficiaries and generators
stand to lose.
Broad features of ABT design.
- It implements the long held view that electricity tariffs should
be two-part comprising of a fixed charge and a separate energy charge.
- It increases the target availability level at which generators will
be able to recover their fixed costs and ROE from 62.79% deemed PLF
at present to 80% (85% after one year) for all thermal stations, 85%
for Hydro in the first year and 77% (82% after one year) for NLC.
- Misdeclaration of availability entails severe penalties.
- 4. It rationalises the relationship between availability level and
recovery of fixed cost.
The draft notification provided for recovery of (annual fixed costs
minus ROE) at 30% availability and recovery of ROE on pro-rata basis
between 30% and 70% availability. This order provides for payment of
capacity charges between 0% and target availability (as indicated in
item 2 above) on pro-rata basis.
- The draft notification had provided for payment of capacity charges
for prolonged outages. This order disallows such payments.
- It delinks the earning of incentive from availability and links it
instead to the actual achievement of generation. Hence incentives will
be earned by generators only where there is a genuine demand for additional
energy generation unlike the prevailing situation, or the proposed draft
received from the GOI, under which it is earned purely because the generator
is available.
- Draft notification linked incentives to equity. This order preserves
the status quo of one paise per kwh per each 1% increase in PLF above
target availability.
- It increases the minimum performance criterion for the earning of
an incentive from 68.5% deemed PLF at present to 80% (85% after one
year) for all thermal stations, 85% for Hydro and 77% (82% after one
year) for NLC.
- It introduces severe financial penalties for grid indiscipline along
with significant rewards for behaviour, which enforces grid discipline
for both generators as well as beneficiaries.
- The order permits market pricing for the trading of surplus energy
by beneficiaries and generators.
- The order urges the GOI to allocate the unallocated capacity a month
in advance so that beneficiaries know their exact share in capacity
in advance and can take steps to trade surplus power.
- It will be implemented in stages from April 1,2000 starting from
the South. The new norm for incentive will however be applicable from
this date for all central stations. In the case of NPC, GOI to decide
applicability of the order.
COMPARISON OF EXISTING TARIFF SYSTEM AND AVAILABILITY
BASED TARIFF
| Sl. No. |
Description of Item |
Existing System |
Draft ABT Proposal |
ABT Order |
| 1. |
Capacity / Fixed Charge |
Annual Fixed Charge (AFC) include :a).
Interest on loan
b). Depreciation
c). O&M
d). Return on Equity
e). Income-Tax
f). Interest on Working Capital |
Fixed charges excluding ROE i.e. all other five
items of the existing system. ROE treated separately |
Capacity charge as per existing system |
| 2. |
Basis of recovery |
Recovered at 62.79% deemed PLF. 50%
AFC at 0% PLF and full recovery at 68.49% deemed PLF. |
FC excluding ROE recovered at 30% availability
on pro-rata basis between 0% and 30% availability.ROE
recovered on pro-rata availability between 30% and 70% |
Pro-rata recovery of capacity charge for :i) NTPC
stations:Between 0 to 80% availability in the first
year and 0 to 85% availability in the second yearii) NLC
StationsBetween 0 to 77% availability in the first year
and 0 to 82% availability in the second yeariii)
NHPC StationsBetween 0 to 85% availability in
the first year and availability in the second year to be announced
by the commission separately. |
| 3. |
Incentives |
Above 68.49% deemed PLF, incentives at 1 paise/KWh
for each 1% increase in PLF. |
Incentive beyond target availability of 70% is
as follows:70% to 85% - 0.4% of equity for each 1% increase
in availability beyond 85%. |
1 paise/KWh/each percentage increase in PLF of
80%/ 85% in the first/ second year for NLC and 85% in the first year for NHPC.. |
| 4. |
Sharing of fixed cost |
Based on actual energy drawals |
Based on allocated capacity |
Based on allocated capacity |
| 5. |
Recovery of variable cost |
Based on actual energy drawals |
Based on Scheduled Energy |
Based on Scheduled Energy |
| 6. |
Deviations from schedule – UI charges |
No penalties for such deviation |
Varying between 0 to 360 paise/kwh for the frequency
range of 50.5 Hz to 49 Hz |
Varying between 0 to 420 paise/kwh for the frequency
range of 50.5 Hz to 49 Hz |
| 7. |
Norms for tariff determination |
GOI Tariff notification |
GOI Tariff notification |
GOI Tariff notification till such time Commission
finalises its views |
| 8. |
Procedure for payment of capacity charge if ABT
is introduced in the middle of a financial year |
Not applicable |
Not specified |
Specified |
| 9. |
Prolonged Outages |
Included in item (2) above |
Provided for payment of adjusted capacity charges |
Does not provide for payment of capacity charges |
| 10. |
Marketing of surplus energy |
Not applicable |
Not specified |
Encouraged and will not require commission’s approval |
| 11. |
Splitting up of capacity and energy charge for
hydro stations. |
Capacity charge covered depreciation and interest
on loan. Energy covered ROE, income tax, O&M and interest on
working capital. |
Capacity charge covered depreciation and interest
on loan. Energy covered ROE, income tax, O&M and interest on
working capital. |
Till such commission notifies peak and off-peak
energy rates for hydro-stations, primary energy charge would be
taken as 90% of the lowest variable charge of the thermal power
station in the concerned region. The balance of total charges would
be recovered as capacity charges. |
| 12. |
Payment of dues to generators |
As per agreements |
As per agreements |
As per orders of the commission |
| 13. |
Applicability |
All central generating stations |
All central generating stations staggered regionwise |
i). ABT implementation is staggered regionwiseii) Fixed charge recovery and basis for incentive payments
revised from 1st April, 2000.iii)
GOI to decide about ABT for automatic power stations. |
| 14. |
PLF for incentives during interim period |
Not applicable |
Not specified |
Till the introduction of ABT in other regions
and after 1.4.2000, the actual PLF for incentive purposes for NTPC
shall be 80% instead of deemed PLF of 68.49%. The PLF in the first
year for incentive purposes for NHPC shall be 85%. |
|